Question 1
ప్రశ్న 1
In earthwork estimation, which statement most accurately describes 'lead' for conveyance of excavated material?
Explanation:
Lead represents the horizontal distance involved in conveying earth or other material between specified locations. For earthwork measurement under IS 1200 (Part 1), the shortest practicable route is used rather than necessarily the route actually travelled. The lead is associated with the movement of material from its source to the designated deposition location. It is distinct from lift, which concerns vertical movement. The applicable schedule and contract determine the chargeable lead intervals, inclusions and rates.
వివరణ:
Question 2
ప్రశ్న 2
Excavated soil must be transported to an approved disposal site. A direct 140 m route is obstructed by a permanent compound wall and cannot be used. The shortest practicable authorized route consists of two horizontal sections measuring 110 m and 70 m. The contractor actually travels 230 m using a different route. What lead should be adopted under the shortest-practicable-route principle of IS 1200 (Part 1)?
Explanation:
IS 1200 (Part 1) requires lead to be based on the shortest practicable route. The geometrically shorter 140 m route is not practicable because of the permanent obstruction. The authorized practicable route measures 110 + 70 = 180 m. The contractor's longer actual route of 230 m does not automatically determine the measured lead. Therefore, the relevant route distance is 180 m before applying the governing measurement-band provisions.
వివరణ:
Question 3
ప్రశ్న 3
Under the lead-measurement provisions of IS 1200 (Part 1):1992, an authorized shortest practicable removal distance is 180 m. Which lead interval should be used?
Explanation:
IS 1200 (Part 1) provides for lead measurement in units of 50 m for distances not exceeding 250 m. The distance of 180 m is greater than 150 m but does not exceed 200 m. It therefore belongs to the exceeding-150-m-and-not-exceeding-200-m interval. The lower 150 m interval cannot accommodate the complete specified distance. This measurement classification must not be confused with different lead-charge intervals prescribed by a departmental SOR.
వివరణ:
Question 4
ప్రశ్న 4
Under IS 1200 (Part 1):1992, the shortest practicable lead for removal of excavated earth is 340 m. How should this lead be classified?
Explanation:
IS 1200 (Part 1) uses 50 m lead intervals for distances not exceeding 250 m. The standard provides a separate lead item for distances exceeding 250 m but not exceeding 500 m. The stated distance of 340 m falls within this separate interval. It should not be divided into additional 50 m measurement bands under this provision. A departmental rate schedule may prescribe a different structure for calculating actual transportation charges.
వివరణ:
Question 5
ప్రశ్న 5
An earthwork lead is measured as 1,320 m along the shortest practicable route. According to the lead intervals of IS 1200 (Part 1):1992 for distances beyond 500 m and up to 5 km, which interval applies?
Explanation:
For leads beyond 500 m and up to 5 km, IS 1200 (Part 1) provides measurement intervals of 500 m. The specified distance of 1,320 m exceeds 1,000 m. It does not exceed the next interval boundary of 1,500 m. Consequently, the applicable interval is exceeding 1,000 m and not exceeding 1,500 m. This classification identifies the measurement item and does not itself establish a transportation rate.
వివరణ:
Question 6
ప్రశ్న 6
Under IS 1200 (Part 1):1992, a lead exceeding 5 km is measured in units of 1 km, with a fractional kilometre of one-half or more counted as one kilometre and a smaller fraction ignored. If the shortest practicable lead is 5.70 km, what measured lead results?
Explanation:
The lead is greater than 5 km, so the specified whole-kilometre rounding provision applies. The distance is 5 km plus a fractional distance of 0.70 km. Since 0.70 km is greater than one-half kilometre, the fraction is counted as a complete kilometre. The resulting measured lead is therefore 6.00 km. The calculation follows the stated IS measurement convention rather than a separate departmental pricing interval.
వివరణ:
Question 7
ప్రశ్న 7
An excavation is divided into two authorized blocks for lead measurement. Block A contains 8 m3 of soil with a lead of 80 m, and Block B contains 12 m3 with a lead of 170 m. Under the supplied project-specific schedule, the complete applicable additional conveyance rates are Rs 25 per m3 for Block A's lead band and Rs 50 per m3 for Block B's lead band. These rates are inclusive for their respective bands and no other charges apply. What is the combined additional conveyance amount?
Explanation:
The two excavation blocks have different lead distances and corresponding scheduled rates. Block A costs 8 x 25 = Rs 200. Block B costs 12 x 50 = Rs 600. Adding the separate block amounts gives Rs 200 + Rs 600 = Rs 800. Applying one rate to the entire 20 m3 would disregard the explicitly supplied block-wise classifications. The calculated result uses the project-specific rates rather than assuming a universal departmental rate.
వివరణ:
Question 8
ప్రశ్న 8
According to IS 1200 (Part 1):1992, which statement correctly describes the initial lift normally included in earthwork excavation where the excavated material is deposited on the surrounding ground?
Explanation:
IS 1200 (Part 1) addresses lift separately from horizontal lead. The standard includes excavation up to 1.5 m below ground level and deposition of the material on the ground in the basic earthwork item. Extra lift is measured in further units of 1.5 m or part thereof. An additional charge cannot be justified solely because some vertical movement occurs within the included depth. The applicable work description and contractual provisions must also be considered when estimating or certifying the charge.
వివరణ:
Question 9
ప్రశ్న 9
Under the IS 1200 (Part 1) extra-lift convention, the initial 1.5 m excavation depth is included, and each further 1.5 m or part thereof forms an additional lift stage. If excavation extends to a maximum depth of 4.00 m below original ground level, how many additional lift stages are encountered?
Explanation:
The first 1.5 m of depth is included in the basic excavation item under the stated convention. The next stage extends from 1.5 m to 3.0 m. The remaining excavation depth from 3.0 m to 4.0 m falls within another additional 1.5 m stage. Thus two additional lift stages are encountered. The quantity of soil associated with each excavation stage must still be measured appropriately rather than charging all excavated material automatically at the deepest stage.
వివరణ:
Question 10
ప్రశ్న 10
A rectangular excavation has a constant plan area of 6.00 m2 and a total depth of 3.30 m. The basic excavation rate is Rs 250 per m3 for the entire authorized volume. The supplied additional lift charges are Rs 50 per m3 for material excavated between depths of 1.5 m and 3.0 m, and Rs 100 per m3 for material excavated between 3.0 m and 4.5 m. These are TOTAL additional charges for their respective depth bands, not cumulative charges to be added together. What is the total estimated amount?
Explanation:
The total excavation volume is 6.00 x 3.30 = 19.80 m3, giving a basic excavation amount of 19.80 x 250 = Rs 4,950. The quantity in the depth band from 1.5 m to 3.0 m is 6.00 x 1.50 = 9.00 m3. Its additional lift amount is 9.00 x 50 = Rs 450. The quantity in the next band from 3.0 m to 3.3 m is 6.00 x 0.30 = 1.80 m3, costing 1.80 x 100 = Rs 180 extra. The total is Rs 4,950 + Rs 450 + Rs 180 = Rs 5,580. The initial 1.5 m band attracts no separate lift charge under the stated conditions.
వివరణ:
Question 11
ప్రశ్న 11
Excavated earth must be carried over a bank and deposited beyond it. The centre of gravity of the excavated material is at RL 98.80 m, and the top of the bank is at RL 104.00 m. Under the special obstruction-related lift measurement provision of IS 1200 (Part 1), what is the lift to be considered?
Explanation:
IS 1200 (Part 1) provides a specific lift measurement rule where earth is carried over a bank or obstruction. The lift in this situation is the difference in level between the centre of gravity of the excavated earth and the top of the bank or obstruction. The two levels are RL 98.80 m and RL 104.00 m. Their difference is 104.00 - 98.80 = 5.20 m. This geometric lift is not simply the excavation depth below original ground level. Any payable lift classification must subsequently follow the applicable schedule and contract.
వివరణ:
Question 12
ప్రశ్న 12
Under the Telangana Revised Standard Data 2026-27 lead-and-lift schedule, which statement correctly describes the adopted mode for lead-charge calculation on the basis of total lead distance?
Explanation:
The Telangana 2026-27 lead-and-lift schedule distinguishes short-distance head-load conveyance from longer-distance mechanical conveyance. It directs adoption of head-load charges for total leads up to 150 m, including the initial lead, irrespective of the actual mode used. For total leads exceeding 150 m, mechanical conveyance charges are to be adopted under the stated schedule. This classification governs the scheduled rate selection rather than the physical method alone. The estimator must also check the applicable material category, initial-lead inclusion and other schedule notes.
వివరణ:
Question 13
ప్రశ్న 13
A project-specific SOR provides cumulative mechanical conveyance rates of Rs 40 per m3 for total lead up to 1 km and Rs 112 per m3 for total lead up to 4 km. The basic earthwork item already includes the first 1 km conveyance charge of Rs 40 per m3. If 28 m3 of eligible material is transported over a total lead of 4 km, what ADDITIONAL lead amount is required?
Explanation:
The total conveyance rate for the 4 km lead is Rs 112 per m3. The first kilometre's charge of Rs 40 per m3 is already included in the stated basic work rate. Therefore the net additional rate is 112 - 40 = Rs 72 per m3. For 28 m3, the additional amount is 28 x 72 = Rs 2,016. The cumulative rate of Rs 112 must not be added in full to an item already containing the initial Rs 40. The calculation prevents double counting of the initial conveyance component.
వివరణ:
Question 14
ప్రశ్న 14
A hypothetical approved mechanical lead schedule specifies a cumulative charge of Rs 120 per m3 for the first 5 km, followed by Rs 18 per m3 for EACH additional kilometre up to 30 km. A separate basic embankment item already includes Rs 45 per m3 for its initial 1 km lead. For a total lead of 12 km and an eligible transported quantity of 20 m3, what is the net ADDITIONAL lead amount?
Explanation:
The first 5 km of total conveyance costs Rs 120 per m3 under the supplied cumulative schedule. There are 12 - 5 = 7 additional kilometres, costing 7 x 18 = Rs 126 per m3. The total charge for 12 km is therefore 120 + 126 = Rs 246 per m3. Since the basic item already includes Rs 45 per m3, the net additional rate is 246 - 45 = Rs 201 per m3. For 20 m3, the additional amount is 20 x 201 = Rs 4,020. The rates are hypothetical values explicitly supplied for this numerical problem.
వివరణ:
Question 15
ప్రశ్న 15
IS 1200 (Part 1) states that earthwork lead-item descriptions shall include loading and unloading. A contractor nevertheless requests separate loading and unloading payments for work whose applicable contract item expressly includes those operations and contains no additional entitlement. What is the correct estimating decision?
Explanation:
IS 1200 (Part 1) requires lead-item descriptions to include loading and unloading. The actual payable scope must nevertheless be established from the governing schedule and contract. In this question, the item expressly includes both operations and provides no separate entitlement. Adding another amount for the same operations would duplicate the cost. Some departmental schedules have specific loading or unloading provisions for particular circumstances, but they must be applied according to their stated conditions. The correct approach is therefore to avoid double charging.
వివరణ:
Question 16
ప్రశ్న 16
Two hypothetical SOR work items have different initial-lead provisions. Item A includes an initial lead of 50 m, while Item B includes an initial lead of 1 km. Both items otherwise permit separate additional conveyance charges where the applicable lead exceeds the included distance. For a total authorized conveyance lead of 800 m, which interpretation is correct?
Explanation:
An initial lead is the transport distance already covered by the stated basic item rate. Item A includes only the first 50 m, whereas the actual lead is 800 m. Its applicable schedule may therefore allow an additional lead charge. Item B includes up to 1 km, and 800 m is within that included distance. Thus no separate additional lead charge arises for Item B under the stated assumptions. This distinction illustrates why there is no single initial-lead distance applicable to every departmental work item.
వివరణ:
Question 17
ప్రశ్న 17
A water-supply project obtains selected earth from an approved location outside the project boundary and transports it for embankment construction. Excavated surplus soil from the project is taken to another authorized location for disposal. Which statement correctly distinguishes these locations?
Explanation:
A borrow area is a designated source from which material is obtained for use in construction or filling. The extracted material may need excavation, loading and conveyance to the work site. A spoil bank or designated disposal area receives surplus excavated material that is not required for the approved construction work. These locations perform different roles in material planning and estimation. Their distances, levels and accepted quantities may influence the applicable lead and lift calculations. Correctly identifying each location is necessary when applying relevant earthwork SOR items.
వివరణ:
Question 18
ప్రశ్న 18
For lead measurement under IS 1200 (Part 1), a large excavation is divided into suitable blocks because different portions of the excavated earth are placed at different disposal locations. Which method is appropriate for determining lead?
Explanation:
IS 1200 (Part 1) provides a block-based approach to earthwork lead measurement. The excavated area is divided into suitable blocks where required. Lead for each block is determined from the centre of that block to the centre of the corresponding placed-earth area. The applicable route must satisfy the shortest-practicable-route principle. This avoids assigning one arbitrary distance to excavation quantities that are moved to different locations. The resulting lead classifications can then be used with the governing SOR provisions.
వివరణ:
Question 19
ప్రశ్న 19
An authorized excavation produces 40 m3 of soil measured in its original in-situ condition. For this problem, its loose transported volume is 1.25 times the in-situ quantity. The applicable conveyance item is expressly payable at Rs 80 per LOOSE m3. What is the conveyance amount, assuming all excavated soil is transported and no other additions apply?
Explanation:
The excavation quantity is measured as 40 m3 in its original in-situ condition. The stated conversion factor gives a transported loose volume of 40 x 1.25 = 50 m3. The conveyance rate is expressly quoted per loose cubic metre. Applying that rate gives 50 x 80 = Rs 4,000. Charging the rate directly on the 40 m3 in-situ quantity would ignore the stated transport-volume basis. The conversion factor is specific to this problem and must not be assumed for all soil types.
వివరణ:
Question 20
ప్రశ్న 20
An embankment requires 60 m3 of completed compacted fill. The project-specific material estimate assumes 1.20 loose m3 of approved borrow soil is needed for each 1.00 m3 of completed compacted fill. The applicable additional conveyance rate is Rs 110 per loose m3 and no other charges are considered. What is the estimated conveyance amount?
Explanation:
The embankment quantity is specified in completed compacted cubic metres. The project assumes that 1.20 loose m3 is needed for each compacted cubic metre. Therefore, the estimated loose borrow material requirement is 60 x 1.20 = 72 m3. The additional conveyance rate is Rs 110 per loose cubic metre. The amount is consequently 72 x 110 = Rs 7,920. This conversion is provided expressly for the problem and is not a universal compaction or bulking factor.
వివరణ:
Question 21
ప్రశ్న 21
A project-specific mechanical conveyance schedule quotes an additional transport rate for bricks of Rs 180 per 1,000 bricks for the applicable lead. A total of 2,500 bricks must be transported, with no other charges. What is the correct amount?
Explanation:
The applicable transport-rate unit is 1,000 bricks rather than an individual brick or a cubic metre. The required quantity is 2,500 bricks. This represents 2,500/1,000 = 2.50 scheduled units. The conveyance amount is 2.50 x 180 = Rs 450. Using the numerical quantity of individual bricks directly with a rate quoted per thousand would produce an incorrect result. The exact unit shown in the lead schedule must therefore be checked before calculating the amount.
వివరణ:
Question 22
ప్రశ్న 22
A project-specific excavation item covers 30 m3 of soil entirely from the depth band of 1.5 m to 3.0 m below ground level. The basic excavation rate is Rs 300 per m3 and includes the initial lead and initial lift only. The authorized additional horizontal lead rate for the applicable band is Rs 55 per m3, while the TOTAL additional lift charge for this depth band is Rs 40 per m3. All 30 m3 qualify for both additional charges, and no other adjustments apply. What is the combined amount?
Explanation:
The basic excavation amount is 30 x 300 = Rs 9,000. The entire specified quantity qualifies for the additional lead rate of Rs 55 per m3. Its additional lead amount is 30 x 55 = Rs 1,650. The same quantity falls within the stated additional lift band, giving 30 x 40 = Rs 1,200 for extra lift. The combined amount is Rs 9,000 + Rs 1,650 + Rs 1,200 = Rs 11,850. The question explicitly states that both additional rates apply to all 30 m3, so no further excavation-stage apportionment is needed.
వివరణ:
Question 23
ప్రశ్న 23
A project has two equally approved surplus-earth disposal sites, with identical environmental, handling and lift conditions. For 60 m3 of material, the complete applicable conveyance rate to Site A is Rs 90 per m3, while the rate to Site B is Rs 115 per m3. How much transport cost is saved by selecting Site A instead of Site B?
Explanation:
The estimated conveyance cost to Site A is 60 x 90 = Rs 5,400. The corresponding cost to Site B is 60 x 115 = Rs 6,900. Both disposal locations are stated to be equally approved and to have identical other conditions. The difference in transport cost is therefore Rs 6,900 - Rs 5,400 = Rs 1,500. Selecting Site A produces a conveyance saving of Rs 1,500 under the supplied conditions. In an actual project, disposal approval and contractual requirements must also be satisfied before choosing a location.
వివరణ:
Question 24
ప్రశ్న 24
A foundation excavation produces 40 m3 of accepted in-situ earth quantity. Of this, 25 m3 is approved for reuse as backfill within the initial lead already covered by the excavation item. The remaining 15 m3 is transported to an authorized spoil bank. For this simplified problem, the separately payable additional spoil-conveyance charge is Rs 110 per m3 on the accepted in-situ quantity disposed of, and no other charges apply. What is the additional conveyance amount?
Explanation:
The total accepted excavation quantity is 40 m3. Of this quantity, 25 m3 is reused within the already included initial lead. The remaining quantity requiring additional conveyance is 40 - 25 = 15 m3. The separately payable rate is expressly stated as Rs 110 per accepted in-situ cubic metre disposed of. The additional amount is therefore 15 x 110 = Rs 1,650. Applying the extra conveyance rate to all 40 m3 would incorrectly charge the locally reused material.
వివరణ:
Question 25
ప్రశ్న 25
A pump-house earthwork estimate contains 30 m3 of basic excavation at Rs 280 per m3, inclusive of the initial lead and lift. Of the excavated quantity, 18 m3 requires additional disposal conveyance over a total lead of 4 km. The supplied cumulative lead rate for 4 km is Rs 110 per m3, of which Rs 35 per m3 for the initial lead is already included in the basic item. Separately, 7 m3 of excavated soil qualifies for an additional lift charge of Rs 50 per m3. Assume all quantities use the stated payable basis, no other charges apply, and all rates are otherwise complete. What is the TOTAL estimated amount?
Explanation:
The basic excavation amount is 30 x 280 = Rs 8,400. The total 4 km conveyance rate is Rs 110 per m3, but the initial Rs 35 per m3 is already included in the basic excavation rate. The net additional lead rate is therefore 110 - 35 = Rs 75 per m3. For the 18 m3 transported to the disposal location, the additional conveyance amount is 18 x 75 = Rs 1,350. The separately eligible additional lift quantity costs 7 x 50 = Rs 350. Adding the three payable components gives Rs 8,400 + Rs 1,350 + Rs 350 = Rs 10,100. The calculation avoids charging the included initial lead twice and applies the additional lift rate only to the eligible volume.
వివరణ:
Answer Key సమాధానాల పట్టిక
-
Question 1 ప్రశ్న 1Answer: B. The horizontal transport distance between the excavation source and the designated place of deposition, measured according to the applicable route and measurement provisions. సమాధానం: B.
-
Question 2 ప్రశ్న 2Answer: D. 180 m. సమాధానం: D.
-
Question 3 ప్రశ్న 3Answer: A. Exceeding 150 m and not exceeding 200 m. సమాధానం: A.
-
Question 4 ప్రశ్న 4Answer: C. Exceeding 250 m and not exceeding 500 m. సమాధానం: C.
-
Question 5 ప్రశ్న 5Answer: B. Exceeding 1,000 m and not exceeding 1,500 m. సమాధానం: B.
-
Question 6 ప్రశ్న 6Answer: D. 6.00 km. సమాధానం: D.
-
Question 7 ప్రశ్న 7Answer: C. Rs 800. సమాధానం: C.
-
Question 8 ప్రశ్న 8Answer: A. Excavation up to 1.5 m below ground level and depositing the earth on the ground are included in the basic earthwork item. సమాధానం: A.
-
Question 9 ప్రశ్న 9Answer: B. Two additional stages. సమాధానం: B.
-
Question 10 ప్రశ్న 10Answer: D. Rs 5,580. సమాధానం: D.
-
Question 11 ప్రశ్న 11Answer: A. 5.20 m. సమాధానం: A.
-
Question 12 ప్రశ్న 12Answer: C. Head-load charges apply for total lead up to 150 m, while mechanical conveyance charges are adopted for total lead exceeding 150 m, as directed by the schedule. సమాధానం: C.
-
Question 13 ప్రశ్న 13Answer: B. Rs 2,016. సమాధానం: B.
-
Question 14 ప్రశ్న 14Answer: C. Rs 4,020. సమాధానం: C.
-
Question 15 ప్రశ్న 15Answer: D. Do not add duplicate charges for operations already included, and apply separate charges only where the governing SOR or contract expressly permits them. సమాధానం: D.
-
Question 16 ప్రశ్న 16Answer: A. Additional lead may arise under Item A, while Item B already covers the entire 800 m lead. సమాధానం: A.
-
Question 17 ప్రశ్న 17Answer: B. The excavation source supplying selected earth is a borrow area, while the authorized surplus-earth disposal or deposition location is a spoil-disposal area or spoil bank. సమాధానం: B.
-
Question 18 ప్రశ్న 18Answer: C. Measure the shortest practicable distance from the centre of each excavation block to the centre of the corresponding placed-earth area. సమాధానం: C.
-
Question 19 ప్రశ్న 19Answer: D. Rs 4,000. సమాధానం: D.
-
Question 20 ప్రశ్న 20Answer: A. Rs 7,920. సమాధానం: A.
-
Question 21 ప్రశ్న 21Answer: B. Rs 450. సమాధానం: B.
-
Question 22 ప్రశ్న 22Answer: C. Rs 11,850. సమాధానం: C.
-
Question 23 ప్రశ్న 23Answer: D. Rs 1,500. సమాధానం: D.
-
Question 24 ప్రశ్న 24Answer: C. Rs 1,650. సమాధానం: C.
-
Question 25 ప్రశ్న 25Answer: A. Rs 10,100. సమాధానం: A.