Please keep at least one language enabled. || కనీసం ఒక భాషను ఎంచుకోండి.
Question 1
ప్రశ్న 1
A municipality must prepare a plan of a small, fairly level, open plot with few obstructions before constructing a valve chamber. Which choice is most suitable if only simple linear field measurements are required?
Explanation:
Chain surveying is especially suitable for small, fairly open areas with comparatively simple details. Its framework is formed by triangles whose sides are measured as linear distances. Suitable survey stations and check measurements improve reliability. Details can be located from survey lines by measured offsets. Dense obstructions and strongly undulating terrain may make this method inefficient. The stated site conditions therefore favour a carefully checked chain survey.
వివరణ:
Question 2
ప్రశ్న 2
A chain-survey framework can be arranged as triangular plots. Which choice gives the BEST-conditioned triangle for reliable plotting when survey-line lengths can be selected freely?
Explanation:
An equilateral triangle has three angles of sixty degrees. It avoids acute intersections that magnify positional error during plotting. In ordinary chain-survey practice, well-conditioned triangles are preferred over long, narrow triangles. A common guideline is to keep their angles approximately between thirty and one hundred twenty degrees. Each of the other listed triangles contains an angle smaller than thirty degrees. The sixty-degree arrangement is therefore the best-conditioned choice.
వివరణ:
Question 3
ప్రశ్న 3
Before fixing main chain-survey stations for a proposed pumping-station compound, the surveyor walks over the site, notes obstructions and makes a rough sketch of candidate lines. What is the main purpose of this operation?
Explanation:
Reconnaissance is a preliminary examination of the survey area. It helps identify clear lines of sight, obstacles and accessible station positions. A rough index or key sketch records the proposed framework and important features. The surveyor uses this information to select appropriate main and subsidiary stations. Reconnaissance does not substitute for measured chain lengths or offsets. It improves the efficiency and reliability of the subsequent field survey.
వివరణ:
Question 4
ప్రశ్న 4
Two subsidiary stations P and Q are selected on different main survey lines because a building corner lies too far from those main lines for convenient offsets. The surveyor measures PQ and takes short offsets from it to the building. How should PQ principally be classified?
Explanation:
A main survey line joins main stations of the survey framework. Subsidiary or tie stations are commonly established on the main survey lines. A line joining suitable tie stations can serve as a tie line. Its purpose includes locating interior features with shorter, more manageable offsets. The measured line PQ is used in precisely this way. A check line, by contrast, is introduced primarily to provide an independent geometrical check.
వివరణ:
Question 5
ప్రశ్న 5
A chain-survey triangle has been plotted from its measured sides. A separately observed proof line between an apex and a marked point on the opposite side differs appreciably from the corresponding plotted length. What is the most appropriate conclusion?
Explanation:
A check or proof line supplies a verification beyond the measured triangle sides. Its independently measured length should agree with the length represented by the plotted geometry within the required tolerance. An appreciable disagreement indicates a possible problem with chaining, booking or plotting. The surveyor should verify the observations and their identification before proceeding. The check line is not a substitute for the main triangle sides. Its principal value is revealing inconsistencies in the survey framework.
వివరణ:
Question 6
ప్రశ్న 6
A surveyor must choose the principal base line for an irregular but accessible chain-survey area. Which proposed location is the most defensible?
Explanation:
The base line is an important control line for developing the chain-survey framework. It is generally selected as a suitably long main line through a convenient part of the area. Clear visibility and reasonably level ground simplify ranging and chaining. Because other plotted positions depend on the framework, the base line should be measured carefully. Excessive obstructions and bends increase the chance of poor control and measurement difficulties. Its location should support well-conditioned triangles rather than merely maximize length at any cost.
వివరణ:
Question 7
ప్రశ్న 7
Main stations A and B are intervisible across an open field. The line exceeds one chain length and an intermediate point must be marked on the straight line AB. Which procedure is most appropriate?
Explanation:
Ranging establishes intermediate points on the intended straight survey line. When the end stations are intervisible, direct ranging is appropriate. The surveyor sights the terminal rods and directs the assistant to adjust the intermediate rod into line. Correct alignment is needed before measuring successive chain lengths. An off-line intermediate point would make the measured route longer than the true straight separation. Reciprocal ranging is primarily needed where direct intervisibility is obstructed.
వివరణ:
Question 8
ప్రశ్న 8
A low hill prevents mutual visibility between terminal stations A and B of a chain line, but two assistants at intermediate positions can see the appropriate neighbouring rods needed for iterative adjustment. Which method should be adopted?
Explanation:
Direct ranging is difficult when the two terminal stations cannot see one another. Reciprocal ranging is suited to such an obstruction when suitable intermediate visibility is available. Two assistants occupy approximate points near the intended line. Each uses visible rods to direct successive adjustments of the other position. Iteration continues until the intermediate points lie on the required straight alignment. The method preserves the intended line despite the obstructed terminal sight.
వివరణ:
Question 9
ప్రశ్న 9
A chainman proposes placing temporary intermediate ranging rods on a curved path between two clearly visible main stations, arguing that total chain length can still be measured. What is the main technical defect?
Explanation:
A main chain line is intended to follow the straight alignment between its defined terminal stations. Ranging locates intermediate points on that line before distance measurements are made. If intermediate points are placed away from it, the chain follows a different route. The sum of those lengths can exceed the true straight separation. Chainages and the locations of subsequent offsets would then be affected. Correct direct ranging prevents this alignment error.
వివరణ:
Question 10
ప్రశ్న 10
In a local horizontal coordinate system, chain line AB runs due EAST from A = (0, 0) m. A valve lies 12 m to the RIGHT of the surveyor walking from A towards B, at a perpendicular-offset chainage of 48 m. What are its coordinates (East, North)?
Explanation:
Chainage is measured from A along the direction of the survey line. The valve's perpendicular foot is forty-eight metres east of A. A surveyor walking east faces east, so the right-hand side lies south. The right offset therefore gives a negative northing of twelve metres. The point has an easting of positive forty-eight metres. Its coordinates are consequently (48, -12) metres in the stated East-North system.
వివరణ:
Question 11
ప్రశ్న 11
A crew wants to erect a perpendicular offset at point O on a chain line using only tape measurements. It marks A at 3 m along the chain line from O, then selects point P such that OP = 4 m and AP = 5 m. What angle does OP make with OA?
Explanation:
The measured sides of triangle OAP are three, four and five metres. They satisfy the Pythagorean relation 3 squared plus 4 squared equals 5 squared. Therefore the triangle is right-angled opposite its five-metre side AP. That right angle occurs at O between OA and OP. Since OA lies along the chain line, OP is a perpendicular offset. This is the familiar 3-4-5 tape method of establishing a right angle.
వివరణ:
Question 12
ప్రశ్న 12
A straight sloping survey segment has measured slope distance 50 m and a vertical rise of 30 m between its endpoints. Assuming correct slope and rise measurements, what HORIZONTAL distance should be used for the chain-survey plan?
Explanation:
A chain-survey plan generally requires horizontal separation rather than the longer slope length. The horizontal distance, vertical rise and slope distance form a right triangle. By the Pythagorean relation, horizontal distance squared equals 50 squared minus 30 squared. This gives 2500 - 900 = 1600 square metres. Taking the positive square root gives forty metres. Recording fifty metres as the horizontal length would overstate this segment.
వివరణ:
Question 13
ప్రశ్న 13
A standard metric chain is 20 m long and has 100 equal links. A chain-line measurement comprises 3 complete chain lengths plus 25 additional links, with the chain assumed correct. What length should be entered in the field book?
Explanation:
Each link in the specified twenty-metre chain has length 20/100 = 0.20 metre. Three complete chain lengths account for sixty metres. The remaining twenty-five links measure 25 × 0.20 = 5 metres. The total recorded length is therefore 60 + 5 = 65 metres. This calculation assumes the standard chain is properly adjusted and used. Link counts must not be confused with numbers of complete chains.
వివరణ:
Question 14
ప్రశ్న 14
While measuring a straight line with a correctly adjusted 20 m chain, the follower confirms 7 complete chain lengths and a final fractional length of 8.6 m. What total horizontal chainage is recorded if all measurements were made horizontally?
Explanation:
Seven complete lengths of a twenty-metre chain represent 7 × 20 = 140 metres. The remaining portion is given as 8.6 metres. It is added to the full-chain distance to obtain total chainage. Thus the total is 140 + 8.6 = 148.6 metres. The calculation presumes that the count of completed chains is correct. A missing or extra chain count would cause a substantial booking error.
వివరణ:
Question 15
ప్రశ్న 15
From a point S at chainage 30 m on a straight eastward chain line, a feature P is located by an OBLIQUE line SP = 10 m making 30° counterclockwise from the forward eastward chain direction. Assuming a plane horizontal geometry, what are the chainage of P's perpendicular foot and its LEFT offset? Use cos 30° = 0.866 and sin 30° = 0.5.
Explanation:
The oblique measurement must be resolved into components along and across the chain line. Its forward component is 10 cos 30° = 8.66 metres. Its lateral component is 10 sin 30° = 5 metres. Adding the forward component to S's chainage gives 30 + 8.66 = 38.66 metres. Counterclockwise from east points north, which is the left side for a surveyor facing east. Therefore the perpendicular foot is at chainage 38.66 metres and the offset is five metres left.
వివరణ:
Question 16
ప్రశ్న 16
At the SAME chainage on a straight chain line, two boundary points are located by perpendicular offsets of 4 m LEFT and 6 m RIGHT. Both offsets are on the same straight normal through the chain point. What is the horizontal distance between the boundary points?
Explanation:
The two features lie on opposite sides of the same chain line. Their perpendicular feet coincide because their chainages are identical. The line joining them therefore lies along the same normal to the chain line. Their separation is the sum of their distances from that common foot. Adding four metres and six metres gives ten metres. Subtracting the offsets would apply only to points on the same side in this particular geometry.
వివరణ:
Question 17
ప్రశ్న 17
A proposed chain-survey triangle has interior angles 20°, 20° and 140°. Why should it be rejected in favour of better-proportioned control geometry where practicable?
Explanation:
The listed angles sum to 180 degrees, so the triangle is geometrically possible. However, it is very narrow, with two angles of only twenty degrees. Such small intersection angles make the position of the apex sensitive to errors in measured sides and plotted intersections. Chain-survey frameworks therefore prefer well-conditioned triangles when terrain permits. Angles around sixty degrees provide more stable plotting geometry. The problem is poor conditioning, not the mere presence of an obtuse angle.
వివరణ:
Question 18
ప్రశ్న 18
A long perpendicular offset of 30 m is set out with a direction error of 1° from the true normal to a straight chain line. Approximately how far ALONG the chain line will the marked point be displaced from its intended perpendicular foot? Use sin 1° ≈ 0.01745.
Explanation:
A small angular error in a long offset creates an unwanted component along the chain line. For a thirty-metre offset tilted one degree from the perpendicular, the along-line component is 30 sin 1°. Using the supplied approximation gives 30 × 0.01745 = 0.5235 metre. This rounds to approximately 0.52 metre. The error demonstrates why excessively long offsets are undesirable. Short offsets reduce the positional effect of a given angular-setting error.
వివరణ:
Question 19
ప్రశ్న 19
A survey crew records a building corner at chainage 62.4 m, perpendicular offset 7.2 m RIGHT, while chaining from main station A towards B. Which entry best preserves enough information to locate the corner on the subsequent plan?
Explanation:
A detail located by a perpendicular offset needs its foot position along the chain line. Chainage 62.4 metres specifies that foot measured from A. The offset length of 7.2 metres specifies the transverse separation. Recording the right-hand side fixes the side relative to the stated direction of chaining. The detail description associates those measurements with the correct building corner. Omitting the chainage, side or chain-line identity would leave the plot ambiguous.
వివరణ:
Question 20
ప్రశ్న 20
A chain-survey triangle has fixed, independently established coordinates A = (0, 0) m, B = (80, 0) m and C = (40, 30) m. A check line is measured from C to midpoint M of AB, and its field length is 31.2 m. The permissible discrepancy for this particular check is 0.1 m. What is the appropriate assessment?
Explanation:
The midpoint M of AB has coordinates (40, 0) metres. Point C has coordinates (40, 30) metres. Their coordinate differences are zero horizontally and thirty metres vertically. The computed length CM is therefore thirty metres. The field measurement differs by 31.2 - 30 = 1.2 metres. This exceeds the stated 0.1-metre tolerance, so the observations and their identification must be checked before accepting the survey.
వివరణ:
Question 21
ప్రశ్న 21
A curved drain edge changes direction frequently near a proposed outfall. During chain surveying, how should the crew locate its shape without assuming the edge itself is a straight chain line?
Explanation:
An irregular feature needs sufficient measured points to represent its actual shape. A nearby surveyed chain line provides the reference for offsets. At each selected chainage, the crew measures and records the distance to the feature. Offsets should be taken more closely where the drain edge bends sharply. The field-book sketch helps associate the observations with the correct points. A single end offset cannot describe a continuously varying boundary reliably.
వివరణ:
Question 22
ప్రశ్న 22
A temporary main chain-survey station beside a pipeline corridor may be disturbed before the contractor returns for setting out. Which precaution best supports its future RELOCATION?
Explanation:
Temporary station marks can be lost or displaced during construction. Reference ties connect the station to nearby features that are likely to remain stable. Two or more suitable measurements can provide geometrical information for recovering the original position. A reference sketch identifies the objects and the relevant distances. These records allow the station to be checked if the peg is damaged. Reliance on one vague description does not provide equally reliable recovery.
వివరణ:
Question 23
ప్రశ్న 23
Two main chain stations are intervisible across a canal, but the crew cannot lay a chain directly over the water. Which field approach is technically appropriate if only accessible ground distances can be measured?
Explanation:
The two terminal stations remain visible, so their alignment can be observed. The canal nevertheless prevents direct physical laying of the chain along the required line. This is an obstacle to chaining rather than an obstruction of terminal intervisibility. Accessible measurements may be arranged in suitable triangles or other verified geometric constructions. The required distance can then be computed from those observations. Estimation by eye would not provide an adequate measured survey result.
వివరణ:
Question 24
ప్రశ్న 24
A chain-survey line climbs a steep irregular slope. The crew must record the HORIZONTAL distance and has only a chain or tape, ranging rods and a plumb bob. Which procedure is appropriate?
Explanation:
Chaining along a steep slope directly measures a sloping distance rather than its horizontal projection. In the stepping method, the tape is held level over successive manageable segments. A plumb bob transfers the suspended endpoint vertically to the ground for the next step. Each step therefore represents a horizontal component of the survey line. Summing the horizontal steps gives the required horizontal distance. This method is useful when one long sloping measurement would require a significant reduction.
వివరణ:
Question 25
ప్రశ్న 25
A distant tree is observed from a known point S on chain line AB by an oblique distance SP, rather than a perpendicular offset. No direction or other measurement to P is recorded. What is needed to locate P uniquely in a horizontal plane without relying on a field sketch?
Explanation:
The oblique distance SP supplies only the radius of a circle centered at S. Many possible positions in the horizontal plane satisfy that one distance. Recording the angle of SP relative to the known chain-line direction identifies the appropriate radial direction. Alternatively, an independent distance from another known point can provide an intersection, subject to resolving possible alternative positions. Chainage of S identifies where the observation originates but does not alone fix P. Complete offset booking must therefore include enough geometric information to determine the detail uniquely.
వివరణ:
Answer Key సమాధానాల పట్టిక
-
Question 1 ప్రశ్న 1Answer: C. Use chain surveying with a well-conditioned triangle framework and offsets to the details. సమాధానం: C.
-
Question 2 ప్రశ్న 2Answer: A. A triangle with angles 60°, 60° and 60°. సమాధానం: A.
-
Question 3 ప్రశ్న 3Answer: D. To undertake reconnaissance and prepare an index or key sketch for selecting a workable survey framework. సమాధానం: D.
-
Question 4 ప్రశ్న 4Answer: B. A tie line used to locate interior details. సమాధానం: B.
-
Question 5 ప్రశ్న 5Answer: C. The discrepancy indicates a possible field or plotting error that should be investigated before accepting the framework. సమాధానం: C.
-
Question 6 ప్రశ్న 6Answer: A. A long, clear and reasonably level main line forming a reliable basis for the triangle framework and accurately measured. సమాధానం: A.
-
Question 7 ప్రశ్న 7Answer: D. Use direct ranging by sighting the end rods and directing an intermediate rod into alignment before chaining. సమాధానం: D.
-
Question 8 ప్రశ్న 8Answer: B. Indirect or reciprocal ranging, with the two intermediate rods successively brought into alignment. సమాధానం: B.
-
Question 9 ప్రశ్న 9Answer: C. The chain would follow a broken or curved route instead of the required straight survey line, giving an incorrect main-line length and unreliable chainages. సమాధానం: C.
-
Question 10 ప్రశ్న 10Answer: A. (48, -12) m. సమాధానం: A.
-
Question 11 ప్రశ్న 11Answer: D. 90°. సమాధానం: D.
-
Question 12 ప్రశ్న 12Answer: B. 40 m. సమాధానం: B.
-
Question 13 ప్రశ్న 13Answer: C. 65.0 m. సమాధానం: C.
-
Question 14 ప్రశ్న 14Answer: A. 148.6 m. సమాధానం: A.
-
Question 15 ప్రశ్న 15Answer: D. Chainage 38.66 m and left offset 5.00 m. సమాధానం: D.
-
Question 16 ప్రశ్న 16Answer: B. 10 m. సమాధానం: B.
-
Question 17 ప్రశ్న 17Answer: C. It is ill-conditioned: its small intersection angles can magnify the positional effects of measurement and plotting errors. సమాధానం: C.
-
Question 18 ప్రశ్న 18Answer: A. 0.52 m. సమాధానం: A.
-
Question 19 ప్రశ్న 19Answer: D. Enter 62.4 m as the chainage on AB and show a 7.2 m perpendicular offset on the right, identified as the building corner. సమాధానం: D.
-
Question 20 ప్రశ్న 20Answer: B. The calculated check length is 30 m; the 1.2 m discrepancy exceeds tolerance and requires investigation. సమాధానం: B.
-
Question 21 ప్రశ్న 21Answer: C. Record offsets at successive suitable chainages, using closer spacing where the edge changes direction rapidly. సమాధానం: C.
-
Question 22 ప్రశ్న 22Answer: A. Record witness or reference ties to stable, identifiable nearby objects and document the station in a reference sketch. సమాధానం: A.
-
Question 23 ప్రశ్న 23Answer: D. Treat it as an obstacle to chaining and use a measured geometric construction or accessible auxiliary triangles to derive the required distance. సమాధానం: D.
-
Question 24 ప్రశ్న 24Answer: B. Use stepping: hold short tape lengths horizontal, transfer the endpoints vertically with a plumb bob, and sum the horizontal steps. సమాధానం: B.
-
Question 25 ప్రశ్న 25Answer: C. An additional independent geometric observation, such as the direction of SP relative to AB, or another suitable distance with ambiguity resolved. సమాధానం: C.