Please keep at least one language enabled. || కనీసం ఒక భాషను ఎంచుకోండి.
Question 1
ప్రశ్న 1
A cement-concrete floor topping is to be laid over an existing RCC slab. The slab surface contains laitance, loose mortar droppings and traces of oil. Which preparation is most appropriate before laying a bonded topping?
Explanation:
A bonded floor topping requires adequate adhesion to the supporting base. Laitance, oil and loose particles can interfere with the bond between the topping and the RCC slab. The surface should be thoroughly cleaned and suitably roughened where required. The specified moisture conditioning and bonding treatment should be carried out immediately before placement. Increasing the topping thickness does not correct an inadequately prepared bonding interface.
వివరణ:
Question 2
ప్రశ్న 2
A cement-concrete floor finish is specified over a hardened concrete base. The contractor proposes leaving the base smooth and completely dry before spreading the topping. Which procedure is more appropriate?
Explanation:
The condition of the supporting base influences the performance of a bonded floor topping. A smooth surface may provide insufficient mechanical interlock. Excessive dryness can draw moisture from the fresh bonding material and affect adhesion. The base should be cleaned, roughened and moisture-conditioned as specified. An approved bonding treatment should then be applied using the procedure appropriate to the selected flooring system.
వివరణ:
Question 3
ప్రశ్న 3
A washroom floor is required to have a uniform downward slope of 1 in 80 towards a floor drain. The horizontal distance from the farthest point to the drain is 4.00 m. What is the required difference in finished floor level between these points?
Explanation:
A slope of 1 in 80 represents one unit of vertical fall for every eighty units of horizontal distance. The horizontal distance in this problem is 4.00 m. The required fall is 4.00/80 = 0.050 m. Converting to millimetres gives 50 mm. The finished flooring should be laid to achieve this specified fall towards the drain without creating unintended depressions.
వివరణ:
Question 4
ప్రశ్న 4
During construction of a cement-concrete floor, workers are unable to maintain the required finished level and thickness consistently across a large room. Which site practice most directly addresses this problem?
Explanation:
Floor screeds and reference marks provide control over surface level and alignment. They guide the laying and finishing of the flooring material. Correctly established references also help maintain the specified topping thickness. In areas requiring drainage, the references should incorporate the approved floor slope. Increasing mixing water is not a suitable method of achieving the required floor geometry.
వివరణ:
Question 5
ప్రశ్న 5
During laying of an in-situ cement-concrete floor topping, the mixture contains excessive water and shows segregation during compaction. Which corrective action best follows proper flooring workmanship?
Explanation:
An in-situ cement-concrete floor topping should possess a consistency suitable for placement and compaction. Excessive water may cause bleeding, segregation and reduced surface durability. Proper compaction should produce a dense topping without bringing excessive water or laitance to the surface. IS 2571 discourages attempts to absorb surplus surface water by spreading dry cement. The defective production procedure should therefore be corrected before satisfactory flooring work continues.
వివరణ:
Question 6
ప్రశ్న 6
For an in-situ cement-concrete floor topping laid separately over a hardened base, which panel arrangement is most consistent with IS 2571?
Explanation:
Panel construction helps control the effects of shrinkage and temperature-related movement in cement-concrete flooring. IS 2571 provides guidance on panel dimensions for toppings laid separately over a base. For separately laid toppings, the maximum panel dimension is generally limited to 2 m under the stated provisions. The panel arrangement should be coordinated with the joints of the supporting concrete. Properly detailed and executed joints reduce the risk of uncontrolled cracking and irregular panel edges.
వివరణ:
Question 7
ప్రశ్న 7
While finishing a freshly laid cement-concrete floor, workers propose sprinkling dry cement powder over visible bleed water and immediately carrying out intensive trowelling. Which action is appropriate?
Explanation:
Bleed water may collect on the surface of freshly placed concrete. Finishing while excessive free water is present can produce a weak surface layer. Sprinkling dry cement to absorb this water is not an acceptable substitute for proper mixture control and finishing. Trowelling should be timed according to the setting and stiffness of the concrete. Appropriate finishing helps achieve the specified smoothness, density and wear resistance of the floor.
వివరణ:
Question 8
ప్రశ్న 8
Under the curing provisions of IS 2571 for in-situ cement-concrete flooring, what minimum period of continuous moist curing is specified after the finished surface has hardened sufficiently to avoid damage?
Explanation:
IS 2571 provides specific curing guidance for in-situ cement-concrete flooring. Freshly finished flooring must first be protected against rapid drying caused by wind and strong sunlight. Once the surface is sufficiently firm, it should be kept continuously moist for at least fifteen days under the stated provision. Suitable methods include ponding or maintaining appropriately wet coverings. This floor-specific requirement should not be confused with different minimum curing periods stated for other concrete or flooring systems.
వివరణ:
Question 9
ప్రశ్న 9
A pump-house wash area is frequently exposed to water, and the approved floor specification requires a slip-resistant finish. The contractor proposes substituting smooth polished tiles solely because they are easier to clean. What is the appropriate decision?
Explanation:
Floor-finish selection should reflect the expected service conditions. Wet areas may require a surface with suitable slip-resistant characteristics. A highly polished tile cannot automatically be assumed to satisfy a specified slip-resistance requirement. Any proposed alternative must be checked against the approved performance and material specifications. The drainage slope and other required flooring details must also be maintained.
వివరణ:
Question 10
ప్రశ్న 10
Under the cement-mortar bedding guidance of IS 1443 for cement-concrete flooring tiles, which thickness range is normally specified for the bedding layer?
Explanation:
IS 1443 provides procedures for laying and finishing cement-concrete flooring tiles. Under its cement-mortar bedding provisions, the bedding thickness is normally not less than 10 mm. The corresponding normal upper limit is 30 mm at any one place. The base must be properly prepared and the mortar spread to obtain the required level and support. Other flooring systems or approved project specifications may prescribe different bedding methods and thicknesses.
వివరణ:
Question 11
ప్రశ్న 11
A rectangular room is to receive square ceramic tiles in a symmetrical pattern. The contractor proposes beginning from an arbitrary corner without considering the resulting narrow cut pieces along the opposite walls. Which procedure is more appropriate?
Explanation:
Tile setting-out controls the appearance and dimensional accuracy of the finished floor. Reference lines establish the intended pattern and alignment of joints. Edge cuts should be planned so that unnecessarily narrow or irregular pieces are avoided where practicable. The joint width should follow the approved specification and the requirements of the tile system. Proper planning also assists quantity estimation and reduces avoidable tile wastage.
వివరణ:
Question 12
ప్రశ్న 12
A flooring specification requires cement mortar bedding in a dry volumetric ratio of 1:4. For a simplified batching calculation, the combined dry ingredient volume is exactly 0.60 m3, with no bulking or volume-change allowance. What are the cement and sand volumes respectively?
Explanation:
The specified mortar proportion contains one part cement and four parts sand. There are five total volumetric parts. The given combined dry ingredient volume is 0.60 m3. Cement volume is 0.60/5 = 0.12 m3, while sand volume is 4 x 0.12 = 0.48 m3. These are the stipulated dry batching quantities and do not represent the guaranteed finished volume of wet mortar.
వివరణ:
Question 13
ప్రశ్న 13
An approved tile-floor detail requires a 20 mm thick mortar bed and tiles having a specified thickness of 10 mm. Assuming no additional adhesive, levelling coat or other layer, what is the total nominal buildup above the prepared base?
Explanation:
The finished floor buildup consists of the thicknesses of the specified layers. The mortar bedding contributes 20 mm. The tile itself contributes another 10 mm. The total nominal buildup is therefore 20 + 10 = 30 mm. This thickness must be considered when establishing the prepared base level and coordinating the finished floor with thresholds and adjoining surfaces.
వివరణ:
Question 14
ప్రశ్న 14
A tile manufacturer specifies a compatible thin-bed adhesive applied over a suitably prepared and levelled substrate. The contractor proposes using isolated thick adhesive spots beneath the tiles instead of the approved application method. Which response is correct?
Explanation:
Tile adhesive systems require compatible substrates and controlled application procedures. The selected adhesive must be used in accordance with its approved technical requirements. Unsupported voids beneath tiles may contribute to cracking or loss of adhesion under service loads. The correct application method should provide adequate bonding and support to the tile. An adhesive specification should not be replaced with an arbitrary fixing method without verification and approval.
వివరణ:
Question 15
ప్రశ్న 15
For cement-concrete flooring tiles laid in accordance with the normal jointing provision of IS 1443, what joint width is generally specified between adjacent tiles?
Explanation:
IS 1443 provides a normal joint width of approximately 1.5 mm for cement-concrete flooring tiles. The tiles should be laid in straight lines and properly bedded to the required level. Joints should be cleaned before being filled with the specified grout. Uniform joints contribute to appearance and satisfactory finishing. This provision is specific to the stated tile-laying system and should not be applied automatically to every ceramic, stone or movement-joint detail.
వివరణ:
Question 16
ప్రశ్న 16
A tiled floor crosses an existing structural movement joint in the supporting concrete. The contractor proposes fixing tiles continuously across the joint and filling the surface line with rigid cement grout. Which treatment is appropriate?
Explanation:
Movement joints accommodate relative movements in the supporting construction. A rigid tile finish laid continuously across such a joint may crack or debond when movement occurs. The floor finish must respect the location and function of the underlying joint. Suitable movement-compatible profiles or fillers should be used as required by the approved detail. Ordinary rigid cement grouting is not an automatic substitute for a specified movement-joint treatment.
వివరణ:
Question 17
ప్రశ్న 17
Natural stone slabs are to be laid over a mortar bed in the entrance hall of a public building. Several slabs have uneven bearing surfaces, and the contractor proposes resting them on isolated mortar lumps while leaving voids below. What should the engineer require?
Explanation:
Stone flooring slabs require suitable support from the bedding system. Isolated mortar lumps can create unsupported areas beneath the slabs. These voids may contribute to cracking, rocking or local damage under concentrated loads. The slabs should be laid to the specified level and pattern with properly formed joints. Bedding preparation and placement must achieve the support and workmanship required by the approved specification.
వివరణ:
Question 18
ప్రశ్న 18
During inspection of a newly laid stone-tile floor, several units rock under foot pressure, show substantial edge misalignment and produce hollow sounds. Which action is most appropriate?
Explanation:
A satisfactory tiled floor should provide stable support to its individual units. Rocking tiles and significant edge misalignment indicate potentially defective laying. Hollow sounds may assist in identifying poorly bonded areas but should be evaluated with the other observed symptoms. The affected units should be inspected and repaired or relaid as appropriate. Surface polishing or cosmetic grout changes cannot restore inadequate bedding support.
వివరణ:
Question 19
ప్రశ్న 19
An in-situ terrazzo floor is specified to receive mechanical grinding and polishing. The contractor proposes beginning aggressive grinding immediately after laying while the cementitious topping is still weak. What is the correct specification-based procedure?
Explanation:
Terrazzo flooring depends on a sufficiently hardened cementitious matrix for satisfactory finishing. Premature grinding can damage the topping or dislodge aggregate particles. The specified curing and hardening period should be completed before the appropriate grinding stages. Grinding, filling of pinholes and subsequent polishing are carried out according to the approved flooring procedure. Proper sequencing helps achieve the required appearance, durability and surface uniformity.
వివరణ:
Question 20
ప్రశ్న 20
Under IS 1200 (Part 11):2024, which measurement rule applies to in-situ cementitious skirting of height 150 mm and in-situ skirting exceeding 150 mm in height, respectively?
Explanation:
IS 1200 (Part 11):2024 contains specific measurement provisions for in-situ finishes. Under these provisions, skirting and runners up to a height of 150 mm are measured in running metres. In-situ skirting exceeding 150 mm in height is measured in square metres. The item description must identify the material, finish and relevant dimensions. The distinction prevents incorrect measurement of different classes of in-situ skirting work.
వివరణ:
Question 21
ప్రశ్న 21
Under IS 1200 (Part 11):2024, how is skirting formed using tile or slab units generally measured under the tile, slab or block finishes provisions?
Explanation:
IS 1200 (Part 11):2024 distinguishes measurement requirements for different floor-finishing systems. Under the tile, slab or block finishes provisions, skirting is measured in running metres with its height stated. The description should identify the tile or slab material and the relevant fixing and finishing requirements. This rule should not be confused with the separate area-measurement provision for higher in-situ skirting. Correct item classification is necessary for accurate quantity take-off and rate application.
వివరణ:
Question 22
ప్రశ్న 22
A rectangular room has floor dimensions of 12.00 m by 8.00 m. The tiled floor contains two unfilled rectangular voids, measuring 0.40 m by 0.50 m and 0.60 m by 0.50 m. Applying the no-deduction rule for voids not exceeding 0.20 m2 under IS 1200 (Part 11):2024, what is the measured tile-floor finish area, assuming no other adjustments?
Explanation:
The gross floor area is 12.00 x 8.00 = 96.00 m2. The first void occupies 0.40 x 0.50 = 0.20 m2. Under the stated measurement rule, this void is not deducted because its area does not exceed 0.20 m2. The second void occupies 0.60 x 0.50 = 0.30 m2 and is therefore deducted. The measured floor-finish area is 96.00 - 0.30 = 95.70 m2.
వివరణ:
Question 23
ప్రశ్న 23
A rectangular room measuring 7.20 m by 5.40 m is to be covered with square floor tiles on a nominal 0.60 m by 0.60 m module. Ignore joint-width effects and assume the dimensions allow an exact whole-tile layout. If 5 percent additional tiles are required for wastage and spares, rounding the purchase quantity upward to the next whole tile, how many tiles should be ordered?
Explanation:
The room area is 7.20 x 5.40 = 38.88 m2. Each tile module covers 0.60 x 0.60 = 0.36 m2. The basic requirement is therefore 38.88/0.36 = 108 tiles. Including the specified 5 percent allowance gives 108 x 1.05 = 113.40 tiles. Since partial tiles cannot be ordered as whole units under the stated assumption, the required purchase quantity is rounded upward to 114 tiles.
వివరణ:
Question 24
ప్రశ్న 24
A floor area of 80 m2 is to receive a uniform 20 mm thick cement-mortar bedding layer in dry volumetric proportion 1:4. For this simplified estimate, assume the combined dry ingredient volume is 1.25 times the theoretical finished bedding volume, with no additional wastage or bulking correction. What volumes of cement and sand are required respectively?
Explanation:
The theoretical finished bedding volume is 80 x 0.020 = 1.60 m3. The specified dry-volume factor is 1.25, giving 1.60 x 1.25 = 2.00 m3 of combined dry ingredients. A cement-to-sand ratio of 1:4 contains five total parts. Cement volume is 2.00/5 = 0.40 m3. Sand volume is four times the cement volume, or 1.60 m3, with no further adjustment under the assumptions given.
వివరణ:
Question 25
ప్రశ్న 25
A detailed estimate includes in-situ cement-concrete flooring, ceramic tile flooring on mortar bedding, natural stone flooring and separately specified skirting. The contractor proposes combining all quantities into one item at a single unspecified rate. Which estimation practice is most appropriate?
Explanation:
Different floor finishes involve different materials, installation methods and workmanship requirements. Their item descriptions should reflect the specified finish, thickness, bedding and relevant treatment. The applicable measurement provisions determine whether each item is measured by area, length or another specified unit. Bedding, dividing strips, skirting and special finishing operations must be checked against the contract's rate inclusions and exclusions. Proper classification and measurement prevent omissions, duplicate charges and incorrect valuation of flooring work.
వివరణ:
Answer Key సమాధానాల పట్టిక
-
Question 1 ప్రశ్న 1Answer: B. Remove laitance, loose particles and contamination, provide a suitable surface key, and prepare the base to receive the specified bonding treatment. సమాధానం: B.
-
Question 2 ప్రశ్న 2Answer: D. Prepare a clean, suitably roughened and dampened base without standing water, and apply the approved bonding treatment before placing the topping. సమాధానం: D.
-
Question 3 ప్రశ్న 3Answer: C. 50 mm. సమాధానం: C.
-
Question 4 ప్రశ్న 4Answer: A. Establish properly aligned level marks, screeds and reference guides to control the finished floor plane and specified thickness. సమాధానం: A.
-
Question 5 ప్రశ్న 5Answer: C. Correct the concrete consistency and production procedure, and place and compact a suitable mix without excessive bleeding or segregation. సమాధానం: C.
-
Question 6 ప్రశ్న 6Answer: B. Divide the topping into suitably proportioned panels, normally limiting a separate topping panel dimension to 2 m and coordinating its joints with the base. సమాధానం: B.
-
Question 7 ప్రశ్న 7Answer: D. Remove or allow excess bleed water to dissipate appropriately, avoid dry-cement dusting, and finish the surface at the proper stage of setting. సమాధానం: D.
-
Question 8 ప్రశ్న 8Answer: A. At least 15 days. సమాధానం: A.
-
Question 9 ప్రశ్న 9Answer: C. Require a flooring product and surface finish satisfying the specified slip-resistance, durability and service requirements before approving any substitution. సమాధానం: C.
-
Question 10 ప్రశ్న 10Answer: B. 10–30 mm. సమాధానం: B.
-
Question 11 ప్రశ్న 11Answer: D. Set out the approved tile pattern and reference lines before laying, coordinating joint widths and edge cuts to obtain a balanced and properly aligned finish. సమాధానం: D.
-
Question 12 ప్రశ్న 12Answer: A. 0.12 m3 cement and 0.48 m3 sand. సమాధానం: A.
-
Question 13 ప్రశ్న 13Answer: B. 30 mm. సమాధానం: B.
-
Question 14 ప్రశ్న 14Answer: C. Apply the approved adhesive using the specified preparation, spreading and bedding method to achieve the required contact and support. సమాధానం: C.
-
Question 15 ప్రశ్న 15Answer: A. 1.5 mm. సమాధానం: A.
-
Question 16 ప్రశ్న 16Answer: D. Continue the movement-joint provision through the flooring system and use the specified movement-compatible joint treatment. సమాధానం: D.
-
Question 17 ప్రశ్న 17Answer: B. Prepare and lay the slabs on the specified bedding with adequate continuous support, correct alignment and properly formed joints. సమాధానం: B.
-
Question 18 ప్రశ్న 18Answer: C. Investigate the affected locations and relay or otherwise rectify defective units using the approved bedding and jointing procedure. సమాధానం: C.
-
Question 19 ప్రశ్న 19Answer: D. Allow the topping to harden and cure adequately, then carry out the prescribed grinding, grouting and polishing sequence. సమాధానం: D.
-
Question 20 ప్రశ్న 20Answer: A. Running metres for skirting up to 150 mm, and square metres for skirting exceeding 150 mm. సమాధానం: A.
-
Question 21 ప్రశ్న 21Answer: B. In running metres, stating the height and the relevant material and workmanship particulars. సమాధానం: B.
-
Question 22 ప్రశ్న 22Answer: D. 95.70 m2. సమాధానం: D.
-
Question 23 ప్రశ్న 23Answer: D. 114 tiles. సమాధానం: D.
-
Question 24 ప్రశ్న 24Answer: A. 0.40 m3 cement and 1.60 m3 sand. సమాధానం: A.
-
Question 25 ప్రశ్న 25Answer: B. Describe and measure the different floor-finishing items according to their materials, thicknesses, bedding, workmanship and applicable measurement rules, while checking contractual rate inclusions to avoid duplicate charges. సమాధానం: B.