A water-main CPM network has independent starting activities A = 4 days and B = 6 days; C = 5 days follows A; D = 4 days follows B; and E = 3 days follows BOTH C and D. All links are zero-lag finish-to-start, with project time zero and no resource restrictions. Which is the controlling path and earliest project completion?
Explanation:
The A–C branch reaches E at time 4 + 5 = 9. The B–D branch reaches E at time 6 + 4 = 10. E must wait for both predecessors and therefore starts at time 10. Its three-day duration gives an earliest completion of 13 days. The B–D–E path controls completion because its duration is 6 + 4 + 3 = 13 days. The other complete path is one day shorter.
వివరణ:
Question 2
ప్రశ్న 2
Use this zero-lag CPM network: A = 4 and B = 6 days start independently; C = 5 days follows A; D = 4 days follows B; E = 3 days follows both C and D. The original project duration is 13 days. If only C increases from 5 to 7 days, what is the REVISED duration and critical path?
Explanation:
Originally the A–C–E route takes 4 + 5 + 3 = 12 days. Increasing C by two days makes this route 4 + 7 + 3 = 14 days. The competing B–D–E route remains 6 + 4 + 3 = 13 days. E must await the longer incoming branch. The revised project duration is 14 days, an increase of only one day. The controlling path switches from B–D–E to A–C–E.
వివరణ:
Question 3
ప్రశ్న 3
An AON pumping-station project has A = 5 and B = 4 days initially; C = 3 follows A; D = 6 follows B; E = 2 follows both C and D; F = 4 follows E. All links are zero-lag finish-to-start. If D is shortened from 6 to 3 days, what is the resulting EARLIEST project completion?
Explanation:
Originally the A–C branch finishes at time 5 + 3 = 8. The B–D branch finishes at time 4 + 6 = 10, giving an original completion of 10 + 2 + 4 = 16 days. Reducing D to three days makes the B–D branch finish at time 7. E must still wait for the A–C branch until time 8. E and F then require another six days, producing completion at time 14. Thus shortening D by three days saves only two project days.
వివరణ:
Question 4
ప్రశ్న 4
A zero-lag AON network has A = 5 and B = 4 days as starting activities; C = 3 follows A; D = 6 follows B; E = 2 follows both C and D; F = 4 follows E. The backward pass uses the earliest project finish as its boundary. What are TOTAL FLOAT and FREE FLOAT of C?
Explanation:
The A–C branch finishes at time 5 + 3 = 8. The B–D branch finishes at time 4 + 6 = 10, so E starts at time 10. C has free float 10 - 8 = 2 days because E's earliest start is unaffected within that allowance. The full project finishes at time 16, and E's latest start is time 10. Consequently C's latest finish is 10 and its total float is also 10 - 8 = 2 days. Both floats are two days under the stated network.
వివరణ:
Question 5
ప్రశ్న 5
In a zero-lag AON network, independent activities A = 3 and B = 7 days are followed by C = 6 after A and D = 2 after B. E = 4 follows BOTH C and D, and F = 2 follows E. Which statement correctly identifies the critical paths?
Explanation:
Activity C finishes at time 3 + 6 = 9. Activity D finishes at time 7 + 2 = 9. Both branches therefore control the time at which E can start. Adding E and F gives a project duration of 9 + 4 + 2 = 15 days. The complete paths A–C–E–F and B–D–E–F each last 15 days. Hence the project has two critical paths.
వివరణ:
Question 6
ప్రశ్న 6
A network contains independent A = 3 and B = 7 days, C = 6 after A, D = 2 after B, E = 4 after BOTH C and D, and F = 2 after E. The original duration is 15 days. If C is reduced from 6 to 3 days while everything else is unchanged, what is the revised project duration and controlling path?
Explanation:
Before the change, both incoming branches to E take nine days. Shortening C to three days makes the A–C branch take 3 + 3 = 6 days. The B–D branch remains 7 + 2 = 9 days. E therefore still starts at time 9 and is followed by F. The revised project duration stays 9 + 4 + 2 = 15 days. B–D–E–F becomes the only critical path.
వివరణ:
Question 7
ప్రశ్న 7
A reservoir project has initial A = 6 and B = 4 days; C = 5 follows A; D = 3 and F = 6 both follow B; E = 4 follows BOTH C and D; G = 2 follows BOTH E and F. All links are zero-lag finish-to-start. What are ES of G and earliest project completion?
Explanation:
C finishes at time 6 + 5 = 11, whereas D finishes at time 4 + 3 = 7. E consequently starts at 11 and finishes at 15. The independent F branch starts after B and finishes at time 4 + 6 = 10. G waits for both E and F, so its earliest start is max(15, 10) = 15. After G's two-day duration, the project finishes at time 17. This computation accounts for both merged branches rather than summing them sequentially.
వివరణ:
Question 8
ప్రశ్న 8
The CPM network has A = 6 and B = 4 as starting activities; C = 5 after A; D = 3 and F = 6 after B; E = 4 after C and D; G = 2 after E and F. Its original project duration is 17 days. If F's duration increases from 6 to 12 days, what is the revised completion and controlling path?
Explanation:
The original A–C–E–G path lasts 6 + 5 + 4 + 2 = 17 days. Increasing F to twelve days makes the B–F–G path last 4 + 12 + 2 = 18 days. The B–D–E–G path remains shorter at 13 days. G must wait for both F and E. The revised project completion is therefore time 18 rather than time 17. The controlling path switches to B–F–G.
వివరణ:
Question 9
ప్రశ్న 9
An AON project has A = 3 and B = 5 days initially; C = 4 after A; D = 6 after B; E = 3 after C and D; F = 2 after C; G = 4 after E and F. In the original schedule C finishes at time 7 and the project finishes at time 18. Suppose only C's ACTUAL finish shifts to time 10, with all remaining durations unchanged. What is the immediate scheduling consequence?
Explanation:
The original B–D branch reaches E at time 5 + 6 = 11. A three-day late finish of C changes its finish from time 7 to time 10. F directly follows C, so F's earliest start shifts by three days from 7 to 10. However, E still waits on D until time 11, not on C until time 10. E then finishes at 14 and G finishes at 18 because F finishes by time 12. This illustrates that a successor can slip without changing the overall project completion.
వివరణ:
Question 10
ప్రశ్న 10
A project has A = 3 and B = 5 days initially; C = 4 follows A; D = 6 follows B; E = 3 follows both C and D; F = 2 follows C; G = 4 follows both E and F. All links are zero-lag finish-to-start and the original finish is day 18. If D alone is shortened from 6 to 3 days, which result is correct?
Explanation:
Originally the B–D branch finishes at time 5 + 6 = 11 and determines E's start. Shortening D by three days causes that branch to finish at time 8. The A–C branch finishes at time 3 + 4 = 7, so E can now start at time 8. E finishes at time 11 while F finishes at time 7 + 2 = 9. G starts at time 11 and finishes at time 15. The project improvement is therefore three days.
వివరణ:
Question 11
ప్రశ్న 11
A water-treatment AON network has A = 4 and B = 3 days initially; C = 6 after A; D = 2 and F = 3 after B; E = 5 after BOTH C and D; G = 2 after BOTH E and F. Project duration is 17 days. B is actually started four days later than its original earliest start, but its duration remains 3 days. Assume no other changes. What is the revised project completion?
Explanation:
A–C reaches E at time 4 + 6 = 10. Delaying B's start by four days makes B finish at time 7. D consequently finishes at time 9, still before C's finish at time 10. F finishes at time 10 after the delayed B, while E finishes at time 15. G therefore starts at time 15 and finishes at time 17. The project finish remains unchanged although both successors of B start later.
వివరణ:
Question 12
ప్రశ్న 12
Consider A = 4 and B = 3 days as independent starts; C = 6 follows A; D = 2 and F = 3 follow B; E = 5 follows C and D; G = 2 follows E and F. All links are zero-lag finish-to-start, and the original duration is 17 days. If the duration of critical Activity A increases from 4 to 6 days, what is the revised duration?
Explanation:
Originally A and C complete the controlling input to E at time 4 + 6 = 10. Increasing A by two days moves that input to time 12. The B–D branch still finishes at time 3 + 2 = 5. Thus E runs from time 12 to time 17. F remains complete well before E, allowing G to run from time 17 to 19. The project completion increases by two days to time 19.
వివరణ:
Question 13
ప్రశ్న 13
A project has TWO independent terminal branches and a common zero-duration FINISH milestone reached only after both finish: A = 4 then C = 7 then E = 2; B = 5 then D = 5 then F = 2. All links are zero-lag finish-to-start. What is the LATEST START of terminal activity F when the backward pass uses the earliest project completion?
Explanation:
The A–C–E branch lasts 4 + 7 + 2 = 13 days. The B–D–F branch lasts 5 + 5 + 2 = 12 days. The common project completion milestone therefore occurs at time 13. As a terminal activity, F has a latest finish of time 13. Subtracting its two-day duration gives F a latest start of time 11. Its earliest start is time 10, confirming one day of total float.
వివరణ:
Question 14
ప్రశ్న 14
AON activities A = 2 and B = 8 days start independently; C = 7 follows A; D = 1 follows B; E = 4 follows BOTH C and D. Initially both branches reach E at time 9 and the project finishes at time 13. If C is shortened to 5 days, which statement is correct?
Explanation:
The original A–C branch takes 2 + 7 = 9 days. After C is shortened, that branch takes only 2 + 5 = 7 days. The B–D branch still takes 8 + 1 = 9 days. Therefore E cannot start before time 9 despite the reduction in C. E's four-day duration leaves completion at time 13. Only B–D–E remains critical after the change.
వివరణ:
Question 15
ప్రశ్న 15
An AON network has A = 6 and B = 5 days initially; C = 4 follows A; D = 7 follows B; E = 3 follows BOTH C and D; F = 2 follows E. The original project duration is 17 days. If B is shortened by 3 days, what is the new project duration and critical path?
Explanation:
Initially B–D finishes at time 5 + 7 = 12, which controls E. The A–C branch finishes at time 6 + 4 = 10. Shortening B from five to two days makes B–D finish at time 2 + 7 = 9. E must now wait until the A–C branch reaches time 10. Adding E and F gives completion at 10 + 3 + 2 = 15 days. The critical path switches to A–C–E–F, and the project improves by only two days.
వివరణ:
Question 16
ప్రశ్న 16
A pump-house network has A = 4 and B = 7 days initially; C = 6 and F = 3 follow A; D = 2 follows B; E = 5 follows BOTH C and D; G = 2 follows BOTH E and F. Original duration is 17 days. If D increases from 2 to 4 days, what is the updated duration and controlling path?
Explanation:
The A–C branch reaches E at time 4 + 6 = 10. Originally the B–D branch reaches E at time 7 + 2 = 9. Increasing D to four days makes B–D reach E at time 11. E then finishes at time 11 + 5 = 16. F finishes at time 4 + 3 = 7 and does not control G. The final G activity takes two days, giving a revised completion of 18 days on B–D–E–G.
వివరణ:
Question 17
ప్రశ్న 17
In a zero-lag AON project, A = 4 and B = 7 days start independently; C = 6 and F = 3 follow A; D = 2 follows B; E = 5 follows C and D; G = 2 follows E and F. The original duration is 17 days. If B increases from 7 to 8 days, which critical-path assessment is correct?
Explanation:
The A–C branch reaches E at time 4 + 6 = 10. Increasing B to eight days makes the B–D branch reach E at time 8 + 2 = 10. Both branches therefore govern E's earliest start. E adds five days and G adds two days to give project completion at time 17. The A–F branch remains much shorter and does not control the finish. Consequently the network now contains two critical paths without any extension of project duration.
వివరణ:
Question 18
ప్రశ్న 18
An AON project requires BOTH terminal activities F and G to be complete: A = 4 and B = 5 days initially; C = 6 follows A; D = 4 follows B; E = 3 follows BOTH C and D; F = 2 follows E; G = 7 follows B. Original project duration is 15 days. If G increases from 7 to 11 days, which result is correct?
Explanation:
The A–C–E–F path takes 4 + 6 + 3 + 2 = 15 days. The B–D–E–F path takes 5 + 4 + 3 + 2 = 14 days. Originally B–G lasts 5 + 7 = 12 days and finishes before the required common completion. Increasing G to eleven days makes B–G last 5 + 11 = 16 days. The project cannot finish until both terminal branches are completed. B–G becomes the only controlling path, extending project duration to 16 days.
వివరణ:
Question 19
ప్రశ్న 19
A network requires BOTH terminal activities F and G: A = 4 and B = 5 days initially; C = 6 follows A; D = 4 follows B; E = 3 follows C and D; F = 2 follows E; G = 7 follows B. Original project duration is 15 days. If C is shortened by 2 days, what is the new project duration and critical path?
Explanation:
Before the change, the A–C branch finishes at time 4 + 6 = 10. The B–D branch finishes at time 5 + 4 = 9. Reducing C to four days makes A–C finish at time 8, so E must instead wait until B–D finishes at time 9. E and F then take 3 + 2 = 5 days, finishing at time 14. The separate B–G branch still ends at time 12. Thus the project now finishes at time 14 on B–D–E–F, improving by only one day.
వివరణ:
Question 20
ప్రశ్న 20
A pipeline CPM network has A = 3 and B = 6 days as independent starts; C = 4 follows A; D = 2 follows B; E = 5 follows BOTH C and D; F = 4 follows C; G = 3 follows BOTH E and F. Its original duration is 16 days. If C increases to 5 days, which statement is correct?
Explanation:
Originally B–D reaches E at time 6 + 2 = 8. The A–C branch reaches E at time 3 + 4 = 7. Increasing C to five days moves A–C completion to time 8. Both predecessors of E now finish at time 8, so E still begins at time 8. E and G require 5 + 3 = 8 additional days, leaving project duration 16. Both A–C–E–G and B–D–E–G are now critical paths.
వివరణ:
Question 21
ప్రశ్న 21
A pipeline project has A = 3 and B = 6 days as starting activities; C = 4 follows A; D = 2 follows B; E = 5 follows BOTH C and D; F = 4 follows C; G = 3 follows BOTH E and F. The original duration is 16 days. If C increases from 4 to 6 days, what are the updated duration and sole controlling path?
Explanation:
Increasing C to six days makes the A–C branch reach E at time 3 + 6 = 9. The unchanged B–D branch reaches E at time 6 + 2 = 8. E therefore starts at 9 and finishes at 14. F starts after C at time 9 and finishes at time 13. G waits for E until time 14 and then takes three days, completing at 17. The controlling path is A–C–E–G rather than either branch involving D or F.
వివరణ:
Question 22
ప్రశ్న 22
A zero-lag CPM network has A = 5 and B = 4 days independently; C = 6 follows A; D = 5 follows B; E = 3 follows BOTH C and D. The original duration is 14 days and B–D–E has 2 days of path float. If B alone is delayed by 3 days with all durations otherwise unchanged, what is the revised project finish?
Explanation:
The A–C–E path takes 5 + 6 + 3 = 14 days. The B–D–E path originally takes 4 + 5 + 3 = 12 days. A three-day delay to B's execution shifts the B branch completion to an elapsed total of 15 days. This exceeds the original controlling path by one day. E must wait for both predecessors, so the revised project finish is time 15. Only two of the delayed three days can be absorbed by the original path float.
వివరణ:
Question 23
ప్రశ్న 23
In an unconstrained zero-lag CPM schedule, two DISJOINT start-to-finish paths each last 18 days and no other path lasts as long. Only one path is shortened by 3 days; all other durations, relationships and resources are unchanged. What is the effect on earliest project completion?
Explanation:
The project finish is determined by the longest remaining start-to-finish path. Initially both disjoint paths last eighteen days and are critical. Shortening one by three days makes that path fifteen days long. The other path still requires eighteen days. Therefore the earliest project completion remains time 18. To shorten the whole project, the remaining critical route must also be addressed.
వివరణ:
Question 24
ప్రశ్న 24
An AON project has two independent branches A = 4 followed by C = 6, and B = 5 followed by D = 5. Both C and D must finish before a COMMON final activity E = 4 days begins. All links are zero-lag finish-to-start, with no other terminal paths. Which single change reduces the earliest project completion by exactly TWO days?
Explanation:
Both branches reach the start of E at time 10: A–C takes 4 + 6 and B–D takes 5 + 5. E then takes four days, making the original project duration 14 days. Shortening only A or only D leaves the other ten-day branch controlling E. Reducing E by one day saves only one project day. Reducing common activity E by two days shortens both complete critical paths to twelve days. It therefore reduces the earliest project completion by exactly two days.
వివరణ:
Question 25
ప్రశ్న 25
A construction project initially has independent A = 3 and B = 4 days; C = 5 follows A; D = 2 follows B; and E = 3 follows BOTH C and D. All links are zero-lag finish-to-start. During method review, a NEW mandatory dependency is approved: D may start only after C is also complete. What is the revised earliest project duration and critical path?
Explanation:
Initially A–C finishes at time 3 + 5 = 8 while B–D finishes at time 4 + 2 = 6. E then starts at time 8 and the original project duration is 11 days. The added C-to-D relationship requires D to wait for both B and C. Consequently D starts at time max(4, 8) = 8 and finishes at time 10. E can now start at time 10 and finishes at time 13. The revised critical path is A–C–D–E, showing that changed logic alone can extend project completion.
వివరణ:
Answer Key సమాధానాల పట్టిక
-
Question 1 ప్రశ్న 1Answer: C. B–D–E; 13 days. సమాధానం: C.
-
Question 2 ప్రశ్న 2Answer: B. 14 days; A–C–E becomes critical. సమాధానం: B.
-
Question 3 ప్రశ్న 3Answer: D. 14 days, an improvement of 2 days. సమాధానం: D.
-
Question 4 ప్రశ్న 4Answer: A. TF = 2 days; FF = 2 days. సమాధానం: A.
-
Question 5 ప్రశ్న 5Answer: B. Both A–C–E–F and B–D–E–F are critical with a 15-day completion. సమాధానం: B.
-
Question 6 ప్రశ్న 6Answer: C. 15 days; B–D–E–F. సమాధానం: C.
-
Question 7 ప్రశ్న 7Answer: A. ES(G) = 15 days; project finish = 17 days. సమాధానం: A.
-
Question 8 ప్రశ్న 8Answer: D. 18 days; B–F–G becomes critical. సమాధానం: D.
-
Question 9 ప్రశ్న 9Answer: C. F's earliest start shifts from 7 to 10, while the project can still finish at time 18. సమాధానం: C.
-
Question 10 ప్రశ్న 10Answer: B. Project duration 15 days, an improvement of 3 days. సమాధానం: B.
-
Question 11 ప్రశ్న 11Answer: D. 17 days. సమాధానం: D.
-
Question 12 ప్రశ్న 12Answer: A. 19 days. సమాధానం: A.
-
Question 13 ప్రశ్న 13Answer: C. 11 days. సమాధానం: C.
-
Question 14 ప్రశ్న 14Answer: B. Project completion remains 13 days, now controlled by B–D–E. సమాధానం: B.
-
Question 15 ప్రశ్న 15Answer: D. 15 days; A–C–E–F. సమాధానం: D.
-
Question 16 ప్రశ్న 16Answer: A. 18 days; B–D–E–G. సమాధానం: A.
-
Question 17 ప్రశ్న 17Answer: C. Both A–C–E–G and B–D–E–G become critical, with the project still taking 17 days. సమాధానం: C.
-
Question 18 ప్రశ్న 18Answer: B. 16 days; B–G becomes the controlling path. సమాధానం: B.
-
Question 19 ప్రశ్న 19Answer: A. 14 days; B–D–E–F. సమాధానం: A.
-
Question 20 ప్రశ్న 20Answer: D. The duration stays 16 days and BOTH A–C–E–G and B–D–E–G are critical. సమాధానం: D.
-
Question 21 ప్రశ్న 21Answer: C. 17 days; A–C–E–G. సమాధానం: C.
-
Question 22 ప్రశ్న 22Answer: B. 15 days; B–D–E becomes the controlling path. సమాధానం: B.
-
Question 23 ప్రశ్న 23Answer: D. It remains 18 days, because the other 18-day critical path still controls completion. సమాధానం: D.
-
Question 24 ప్రశ్న 24Answer: C. Shorten common activity E from 4 to 2 days. సమాధానం: C.
-
Question 25 ప్రశ్న 25Answer: A. 13 days; A–C–D–E. సమాధానం: A.